Edinburgh’s £290m housing regeneration plans stall as Graham and Cruden deals collapse
Plans for the Meadowbank site have stalled
Two of Edinburgh’s biggest council-led housing regeneration projects will be handed to new contractors after the development agreements behind them broke down over costs and risk.
Projects in Meadowbank and Fountainbridge, which were due to deliver 1,169 homes in total, are now facing delays, with the City of Edinburgh Council needing to find new delivery arrangements for both.
The setback comes about a year after councillors authorised officers to finalise development agreements with both construction partnerships. Both developments were expected to start on site this year, after long pre-construction design and planning programmes.
Meadowbank partnership ends over costs
Formally known as the Edinburgh Meadowbank Group (EDMB), a consortium led by Graham, with Miller Homes and Panacea Property Development, was appointed in 2022 as pre-development partner for Meadowbank.
The £120m development would deliver 705 homes around the rebuilt Meadowbank Sports Centre. The council’s aim was one of the capital’s greenest neighbourhoods, combining low-car, low-carbon design with energy-efficient homes. The planned mix was 216 one-bedroom homes, 337 two-bedroom homes, 138 three-bedroom homes and 14 studios. Of these, 27 would be wheelchair accessible.
Talks over construction costs continued until the partnership was terminated. The council’s finance and resources committee, which met on November 17, was told that the lack of agreement on costs had caused significant delays. The report said the agreement had ended under its contractual terms and that the development would continue with an alternative supplier.
A September update had already flagged the problem. Around £32.9m of site remediation and affordable housing construction was expected in 2026-27, but that spending was held up because costs hadn’t been agreed.
Designs by 7N Architects for the Fountainbridge site
A council spokesperson said market conditions made it impossible to agree terms for the delivery stage, and that both sides had agreed to end the partnership.
The spokesperson said: “The council has worked with the Meadowbank Consortium to prepare proposals for the site. Unfortunately, due to market conditions, it has not been possible to enter into an agreement for the delivery stage of the project, and the parties have mutually agreed to bring the partnership to an end.
“The council is now working with one of its framework contractors to deliver the affordable housing as a first stage of the development.”
The consortium said the widening affordability gap led it to step aside.
A representative from the EDMB consortium said: “Due to the widening affordability gap facing medium and high-density housing, the consortium will step aside from the development in agreement with the City of Edinburgh Council, allowing them to review future delivery options for the site.”
Fountainbridge risk-sharing talks fail
The Fountainbridge deal has also fallen through. Cruden Homes and development partner Buccleuch Property were selected in 2021 to turn the former brewery site beside the Union Canal into a mixed-use neighbourhood. The project is valued at £170m and would provide 464 homes, 186 of them affordable.
The sticking point was how development risk should be shared. In September, council officers reported that standard terms had not been agreed with the contractor on this issue, and that it had withdrawn from the development agreement. The latest report confirms that the council expects to take the scheme forward with another supplier.
Both partnerships had won pre-development contracts, worth about £1m at Meadowbank and £1.1m at Fountainbridge. A third Edinburgh development, at Coatfield Lane, has also been delayed after rising costs forced a redesign.