Sprinkler retrofit programme approved for Fife tower blocks

Sprinkler retrofit programme approved for Fife tower blocks

Fife Council’s Cabinet Committee has agreed a landmark decision to further enhance fire safety across its high-rise housing stock.

Following the Grenfell Part 2 Inquiry and ongoing reviews of fire safety standards, members approved recommendations to retrofit water-based sprinkler systems in all flats at Swan & Memorial Courts, Methil.

Subject to successful evaluation, the programme will then extend to the council’s remaining 10 tower blocks across Fife over the next five years.

The initial investment of £1.14 million for the Methil blocks will be met from the Housing Revenue Account (HRA) Capital Plan. A further £6m would be required for the work to Fife’s other tower blocks, with funding to be considered in the 2027 review.

Committee members were given assurances that the works will be delivered in consultation with tenants and residents’ associations to minimise disruption and ensure clear communication throughout.

Housing spokesperson, Councillor Judy Hamilton, said: “This is a major investment in safety and resilience. While the tower blocks are safe, and fully comply with regulations and the findings of the Grenfell Part 1 Inquiry, these additional measures will further protect lives and modernise our housing stock.

“There is currently no legal requirement to retrofit sprinklers in existing high-rise buildings, but we know that retrofitting sprinklers is a practical, proven measure that will give residents confidence in the safety of their homes for decades to come.

“This decision reflects our determination to go beyond minimum standards and set a benchmark for fire safety in Scotland. It’s about reassurance, responsibility and doing the right thing for our communities.”

The Scottish Fire and Rescue Service has welcomed the move, providing a statement of support in the committee report that it “will undoubtedly have a positive impact on the life safety of occupants”.

The full programme is expected to run until 2030, with progress reports brought back to the council’s Cabinet Committee in 2026.